Jingneng Xiuzhou Base Starts Production Ahead of Schedule

wechat.svg

Recently, Phase I of Jingneng Xiuzhou Base completed main construction ahead of schedule and officially went into production, with the first SiC power module successfully launched.

微信图片_2025-12-25_162819_871.png

Construction started on February 5, 2024.The project cycle was much shorter than the industry average.Located in Jiaxing National High-tech Zone, the base covers 6.36 hectares (95.4 mu).It is Jingneng’s third professional production base after Yuhang and Wenling.

Phase I has an annual capacity of 600,000 units of automotive-grade power modules.The production line uses an innovative island-style automation layout for high efficiency and strong flexibility, supporting fast switching for multi-product manufacturing.During construction, Jingneng adopted a “build while producing” strategy with multi-zone coordination and phased production, greatly shortening the ramp-up period and enabling early commissioning.

微信图片_2025-12-25_162936_058.png

Jingneng has secured project designations from multiple customers and is scaling mass deliveries, with growing market share.Xiuzhou Base will continue ramping up capacity to become a core R&D and manufacturing platform for high-performance automotive-grade power modules.

Zhejiang Jingneng Microelectronics Co., Ltd., founded in June 2022,is the power and AI semiconductor platform of Geely Technology Group.Leveraging the Group’s global industrial resources,it has built a leading R&D and manufacturing system,serving core industries including electric vehicles, sustainable energy and AI infrastructure.

Adhering to a user-centric philosophy, Jingneng Microelectronics focuses on technological innovation.It has built a multi-dimensional technology layout from chip design and module development to system integration, providing competitive differentiated solutions and driving the intelligent and green upgrading of the industry.